1. BACKGROUND
The existing water supply in the Greater Dublin Region is undertaken by seven
local authorities within their respective functional areas. Two local authorities
have responsibility for water production in the Region.
Historically, water demand in the Region has been rising steadily. As each
new increment of production capacity has been added, it has been absorbed almost
immediately to meet suppressed demand. Given that there is a finite limit to
the economic and practical water resources available in the Region, it was clear
that this demand growth pattern of 2% increase per annum is unsustainable in
the long term particularly since it was believed that leakage accounts for a
large proportion of the demand. At the same time, there was an urgent need for
residual capacity in the Region to meet demand growth, both domestic and industrial/commercial
in the light of significant economic growth in the period 1994-1996.
Against this background, the Department of the Environment commissioned a Strategic Study of the Water Supply of the Greater Dublin Region in January 1995. The Study was carried out by Compagnie Générale des Eaux (General Water Company) in association with M.C. O'Sullivan & Co.Ltd. with the Final Report submitted in January 1996. The main purpose of the study was :
a) to assess present levels of service and water supply problems in the Region
b) to provide for the cost effective future development of the water supply
network for the Region.
2. PRELIMINARY DATA COLLECTION
In order to develop a comprehensive understanding of the existing system,
its capacity and shortcomings, an extensive data collection exercise was undertaken.
In approaching this exercise, the Study Team objectives included :
The principal areas of data collection and analysis were :
3. ASSESSMENT OF CURRENT DEMAND
During the study period the average demand in the region was determined from
the combined production capacities of the 4 treatment plants, all of which were
operating at full capacity. The daily output was calculated at 437.5 Ml/day.
During this period, throttling as a means of demand suppression was practised
throughout the region. It follows that there was a degree of suppressed demand
which was taken as being 15 Ml/day giving a true demand of 452.5 Ml/day. The
estimated population in 1995 was taken as 1.22 million persons.
Extensive investigations were carried out in an effort to assess the components
of demand in the region. Reference was also made to figures from the UK and
Europe for average per capita consumption and typical usage by commercial enterprises.
The estimated breakdown of present demand was established as follows :
For a minimum pressure standard of 15m, it was estimated that some 127,000
properties or 34% of the total had unsatisfactory pressure.
There are approximately 6,000 commercial consumers in the region with fixed
charge accounts. There are no accurate estimates of consumption for these and
the estimate used was derived from the amount charged at commercial rates. In
addition, there are approximately 25,000 rateable properties which are uncharged
and can be described as unmeasured non-domestic users. It is believed
that these premises are typically professional offices and shops.
Consumption was estimated arbitrarily on the basis of 6 persons/property and
60 litres/person, giving 360 litres/property/day. Reference to UK practice in
this regard was not particularly helpful in this context, showing a wide variation
and is generally regarded as a balancing figure taken along with other unknown
components such as per capita consumption and leakage. The estimate of unmetered
industrial and commercial consumption ultimately derived was 17.1 Ml/day.
4. FUTURE DEMAND FORECAST
A future demand forecast to the horizon of 2016 was developed having regard
to the following component elements :
Existing Industrial/Commercial Demand; projected change taking account of increased output, environmental pressures and application of the " polluter pays principle ".
4.1 Future Domestic Demand
It was recognised that some growth would occur in domestic demand in the region
based on the rate of growth in house numbers, the continued fall in house occupancy
rate and increased prosperity. Population growth from historical census data
and the rate of growth of residential development was anticipated to grow in
urban areas. An overall figure of 0.6% per annum was adopted for the Region
as a whole equivalent to approximately 14% from 1994 to 2016. It was recognised
that the bulk of this would take place in peripheral areas.
Per capita consumption is also influenced by increased prosperity, additional
appliances, increasing use of power, showers and recovery from suppressed demand.
Even when offset by domestic conservation policies, a figure of 0.6% per annum
compound growth in per capita consumption was assumed. This rate of growth was
identified from a study of micro-components of consumption in England and Wales
as part of the National Rivers Authority's National Water Resources Strategy.
The effect is to increase per capita consumption from 135 l/h/day in 1994 to
154 l/h/day by 2016.
4.2 Future Industrial Demand
Water consumption in existing industry might be expected to grow in a high performance economy associated with increased production. However, opposite factors which will tend to reduce consumption will include water saving measures associated with improved housekeeping, increased charges for effluent treatment and greater efficiency. Accordingly, no change in current demand for existing industry is assumed.
National and local policies promote continued industrial development throughout
the Region with extensive areas of lands zoned for industrial development totalling
approximately 1,800 hectares currently. In all, it was considered prudent to
provide for an increase of 48 Ml/day over the study period to cater for industrial
development. This was distributed throughout the Region according to the areas
available for development and the types of industry being encouraged in the
particular areas.
4.3 Future Loss Objectives
The other critical factor in estimating future demands relates to the projected
level of losses. Based on an active and aggressive leakage programme discussed
late, the following assumptions have been made as regards future losses :
5. WATER QUALITY
Water quality issues in the context of the Study were considered in terms
of compliance with the EU Drinking Water Directive (80/778/EEC). In relation
to distributed water quality, the following observations were made :
The most significant water quality issue relates to occasional failures
in bacteriological standards due to the two open service reservoirs and the
presence of significant numbers of ball hydrants in the distribution system.
These can permit contamination of the supply.
The corrosivity of the water supply in Dublin is evident from the extent of
corrosion of the cast iron pipe network and is reflected in the values for Langelier
Index and Ryznar Index for the individual supplies. Notwithstanding this, the
expected elevation of metal concentrations in the supply, in particular iron,
lead and to a lesser extent copper are not borne out by the analytical results.
However, distribution pipe samples clearly exhibit evidence of the corrosive
nature of the water. The deposition of coatings within the supply pipes may
have the effect of limiting the transfer of metals to the water during quiescent
supply conditions.
6. DEMAND MANAGEMENT AND LEAKAGE CONTROL
The estimation of current losses summarised above indicated average losses
of 44% with the assumption that 5% relates to customer side losses and 39% to
distribution losses. this is equivalent to an average leakage level of 27 l/property/hour.
Statistics from England and Wales indicate supply pipe leakage in the range
38-80 l/property/day with an industry average of 50 l/property/day. This is
considered to comprise background leakage from joints and fittings of the order
of 20 l/property/day with the balance associated with undetected bursts.
The factors contributing to excessive leakage in the Dublin Region include
the following :
A 5-year programme to reduce leakage to 20% would include the following components
:
The objectives recommended would involve reduction in total losses to 101
Ml/day at the year 2000 and further reduction to 90 Ml/day, notwithstanding
the increases in demand in the meantime, by the year 2016. This would require
a continued active leakage policy based on flow measurement, active leak detection,
pressure management and infrastructural renewal.
Ultimately, the whole of the distribution network must be subject to regular
leakage monitoring by appropriate district metering, with water supply areas
monitored via the telemetry system. It is likely that continued infrastructure
renewal will be required to include replacement of weak communication pipes
or rehabilitation of mains with a burst rate of in excess of 5 per kilometre
within a 5-year period.
Reduction in customer losses is also required to meet the medium and long
term demand objectives. A systematic approach to detection of customer losses
and enforcement of waste notices requiring repair is required. A uniform procedure
is recommended to be adopted across the Region for active enforcement of these
notices. At the same time, a programme to increase public awareness of water
conservation issues will be required.
7. TELEMETRY SYSTEM
The existing telemetry system covers key strategic reservoirs and flow meters.
In the short term, additional metering and pressure monitoring will be established
throughout the network to cover discrete water supply areas and ultimately extending
to the full district meter areas. The extension of the telemetry system would
be developed to cover these elements and to integrate the systems used at the
treatment plants.
8. APPLICATION OF PRINCIPLES
The Strategy Study recommendations have been adopted by the Minister and similar
principles will be applied to all sanitary authorities. A guidance manual on
water distribution network management and leakage control has also been issued.
A preliminary water audit to establish the level of UFW is now required before
any capital investment in new infrastructure is approved. Central Government
will pay up to 50% of the cost of preparing network management plans or strategic
studies and will fund up to 100% of the cost of leakage reduction/control measures
on a project basis of limited duration and to meet specific targets. Up to 50%
of the cost of mains rehabilitation/replacement from approved water conservation
proposals will also be funded.